Closure Planned for Interstate 229 Northbound Off-ramp at Minnesota Avenue in Sioux Falls

SIOUX FALLS, S.D. – Motorists should be aware that a closure is scheduled to begin at 9 a.m. on Monday, Aug. 14, 2023, on the Interstate 229 northbound off-ramp at Minnesota Avenue (exit 3).

Weather dependent, this work will require the off-ramp closure to be in place through Monday, Aug. 21, 2023.

The project will repair the concrete surfacing at the exit ramp that was damaged by recent excessive heat.

This construction work is part of a larger project to repair various concrete pavements in the Sioux Falls area.

The prime contractor on this nearly $1 million project is Dakota Contracting Corporation of Sioux Falls, SD.